Dealing with Construction Permits
Dealing with Construction Permits measures all procedures, cost, and time required for a business to build a warehouse. The warehouse is assumed to have two storeys and will be built in Quezon City. According to the latest Doing Business Report, the entire process takes 29 steps and 84 days in the Philippines. (Those with (*) indicate steps done simultaneously with another.) Though the team committed to cut this down to 16 steps and 71 days, it was able to reach 17 steps and 61 days.